Rate Schedule
Battle River Power Coop Distribution Tariff
Effective August 26, 2024
Rate - Rural Farm/Acreage BR240
Breaker Size | 3 kVA | 5 kVA | 7.5 kVA | 10 kVA | 15 kVA | 25 kVA | >25 kVA |
Monthly Operating | $67.94 | $67.94 | $85.24 | $99.83 | $127.68 | $183.07 | $4.73*/kVA |
* $183.07 $4.73 per kVA above 25 kVA
Demand Services are reset monthly with a minimum of the transformer capacity of 25 kVA**
Rate - Demand Industrial BR410
0-50 kVA - $4.88/kVA | 51-500 kVA - $3.05/kVA | >500 kVA - $2.08/kVA |
Rate - Residential DT rate BR120
| Distribution Component |
Service Charge per Unit | $0.9350/day |
All kWh Delivered | 3.0250 cents/kWh |
|
Individual metered residential sites shared transformers |
Rate - Oil and Gas BR510
Service charge per kVA per day | $0.6450 |
Daily charge | $0.5200 |
Rate - Idle Service BR110C
No Size Requirement
Monthly Operating | $38.55 |
Additional Pole | $1.76 |
Rate - Street Lighting (Investment Option) BR310
Subdivision Only |
Based on fixture cost, watts and type (i.e. led) |
Once investment is paid rates decline to maintenance only pricing |
Miscellaneous Charges
Disconnect Fee | $110.00 | |
Reconnect Fee | $110.00 | |
On Site Meter Platter Test | $250.00 | Charged only at member request |
Charge to go on/off idle | $60.00 | Must be idle for 12 month period or priced at service call @ $250.00 |
First energize (Subdivision) | $300.00 | |
Late Payment Fee | 2% | |
Doorknocker Charge | $90.00 | |
Electricity Rates
| Energy Affiliated Retail | Regulated Rate Option |
Refer to Energy Contract | 8.850 cents/kWh | See Regulated Rate |
Fixed Charges | $7.00 | $7.00 |
UFE & Line Loss | Included | Included |
Battle River Power Coop Transmission Rate
The current FortisAlberta AUC approved rate including all applicable rate riders, and in accordance with Battle River Power Cooperative Terms and Conditions.
Load Settlement
Distribution Basic Daily Charge | $0.045/day |
Distribution Adjustment Rider | 0.00% |
Total Load Settlement per day | $0.045/day |